Five parts of a comparison report, as they appear in the delivered HTML page: title block, result summary, register comparison, drawing comparison with graded findings, and specification consistency.

NABU Compare
Comparison report · SF-C-CMP-01 · Excerpt
Project
Sampleford Court, Block C
14-storey residential tower with podium. Architecture package.
Stages compared
Tender issue12 March 2026 Contract issue29 June 2026
Registers, drawings and specification volumes of both issues.
Prepared
8 November 2026
Status: issued for review

1Result summary

Each document in either register is listed below or named in the exception lists in Part 6 of the full report; per-discipline sums equal the totals.

1,284Documents compared
312Changed
41Added in contract
17Superseded
23Major findings
96Medium findings
193Minor findings

312 graded findings across 312 changed documents. Grades reflect the effect of what is drawn and its indicative cost; they are a reviewer's aid, not a valuation.

2Register comparison

Each row pairs a tender document with its contract counterpart by number, then by title where the number changed. Twelve rows shown of 1,284; the full table is filterable in the report.

Number Title Tender rev / date Contract rev / date Result
SF-C-A-0001Drawing list and cover sheetP0306 Mar 2026C0122 Jun 2026Revision raised P03 to C01
SF-C-A-1001Site planP0206 Mar 2026C0122 Jun 2026Revision raised P02 to C01
SF-C-A-2100Podium ground floor planP0206 Mar 2026C0122 Jun 2026Revision raised P02 to C01; 14 drawn differences
SF-C-A-2103Level 3 floor plan, typicalP0206 Mar 2026C0222 Jun 2026Revision raised P02 to C02; 3 drawn differences
SF-C-A-2114Roof and plant planP0106 Mar 2026C0122 Jun 2026Title changed from "Roof plan"
SF-C-A-3001Elevations north and eastP0206 Mar 2026C0122 Jun 2026Revision raised P02 to C01
SF-C-A-4002Section B-BP0206 Mar 2026C0122 Jun 2026Revision raised P02 to C01; content unchanged
SF-C-A-5120Door scheduleP0206 Mar 2026C0222 Jun 2026Revision raised P02 to C02; 6 rows changed
SF-C-A-5301Wall typesP0106 Mar 2026C0122 Jun 2026Revision raised P01 to C01; type W-12 rating changed
SF-C-A-6210Lift lobby details, typicalnot in tenderC0122 Jun 2026Added in contract
SF-C-A-2103ALevel 3 ceiling planP0106 Mar 2026not in contractSuperseded by SF-C-A-2203
SF-C-A-2203Level 3 reflected ceiling plannot in tenderC0122 Jun 2026Added in contract; supersedes SF-C-A-2103A
Dates are the drawing dates in the title blocks. Register issue dates: 12 March 2026 (tender), 29 June 2026 (contract).

3Drawing comparison

SF-C-A-2103, Level 3 floor plan, typical. Excerpt at grids C to E / 3 to 5, apartments 3.05 and 3.06 with the central corridor. Tender issue on the left, contract issue on the right; removed or moved elements are shown dashed on the contract crop.

Tender issueSF-C-A-2103 · P02 · 06 Mar 2026
C D E 3 4 5 D-07 W-12 1,600 APT 3.05LIVING APT 3.06LIVING CORRIDOR 3.01 LOBBY 3.02 STORE 3.07 N
Contract issueSF-C-A-2103 · C02 · 22 Jun 2026
C D E 3 4 5 D-07 W-12 1,150 APT 3.05LIVING APT 3.06LIVING CORRIDOR 3.01 LIFT LOBBY 3.02 STORE 3.07 1 2 3 N
  • Contract issue, as drawn
  • Tender position, removed or moved
  • Structural grid
  • Finding, numbered below
  1. MajorDoor D-07 relocated; corridor narrowed
    Door D-07 relocated 600 mm east; corridor 3.01 south wall moved 450 mm north between grids C and E; corridor width reduced from 1,600 mm to 1,150 mm. Door schedule SF-C-A-5120 row D-07 is unchanged. Clear width at the door approach and the accessible route to lobby 3.02 to be confirmed by the designer.
    ArchitectureEgress and accessLevel 3, typical floors 3 to 13Effect: MajorCost: Medium
  2. MediumWall W-12 extended to grid 5
    Wall W-12 extended 1,800 mm south to meet the party wall at grid 5, enclosing store 3.07 on four sides. Wall type W-12 now shown as a 60-minute rated partition on SF-C-A-5301; the Level 3 plan hatch still reads as 90 minutes. Repeats on eleven typical floors.
    ArchitectureFire compartmentationLevel 3, typical floors 3 to 13Effect: MediumCost: Medium
  3. MinorRoom name changed
    Room 3.02 renamed from "Lobby" to "Lift lobby". Tag text only; no change to the drawn enclosure, finish or door set. Matches the new sheet SF-C-A-6210, Lift lobby details.
    ArchitectureAnnotationLevel 3Effect: MinorCost: Minor

Dimensions are scaled from the drawings and rounded to 50 mm; they indicate the order of the change and are not setting-out dimensions. Grades are indicative, from the drawings alone.

4Specification consistency, contract issue

Within the contract issue, each specification clause that states a drawn or scheduled property is read against the drawing or schedule that shows it. Four of 212 checked clauses shown.

Clause Specification states Drawing or schedule shows Result
Vol. 2, 4.3.2Internal apartment doors: 44 mm solid-core leaf, hardwood lipping.SF-C-A-5120, row D-07: 44 mm solid-core leaf.Agrees
Vol. 2, 5.1.4Corridor partitions type W-12: 60-minute fire resistance, full height to slab.SF-C-A-5301: W-12 at 60 minutes. SF-C-A-2103 C02: W-12 hatched as 90 minutes.Discrepancy between plan and wall-type sheet
Vol. 3, 2.2.1Corridor floor finish: sheet vinyl, 2.0 mm, slip resistance class as scheduled.Finishes schedule SF-C-A-5410, room 3.01: vinyl 2.0 mm.Agrees
Vol. 2, 4.6.3Apartment entrance doors: lever handles throughout, accessible pattern.SF-C-A-5120, row D-07 hardware set H-3: knob set.Discrepancy between clause and schedule

Consistency is checked within one issue only. A discrepancy is reported as found; which document governs is a matter for the contract, not for this report.

5What this report does and does not say

It does say

Which documents exist in each issue, how each one was paired, and what changed between them as drawn, scheduled or written. Each change is named by element, located by grid and level, and graded for its effect and indicative cost. Every document that could not be compared is listed with the reason.

It does not say

Whether a change is correct, approved or priced. Dimensions are scaled from drawings, not measured on site. Grades are a reviewer's aid for ordering attention, not a valuation or an instruction. Where a clause and a drawing disagree, the report records the disagreement; it does not decide which governs.